The government faces an estimated Sh109.4 billion funding requirement to complete four major dam projects that remain stalled years after construction and financing arrangements began.
National Treasury sector reports for the 2027/28 budget cycle show that Arror, Kimwarer, Itare and Soin-Koru dams have a combined estimated cost of Sh132 billion. Cumulative spending stood at about Sh22.6 billion by June 2026, leaving the Sh109.4 billion balance.
The figure represents the difference between the projects’ estimated costs and reported cumulative expenditure. It is not a confirmed single allocation or final financing package, and the eventual bill could change if contracts, designs, interest payments or compensation arrangements are revised.
Arror Multipurpose Dam in Marakwet East, Elgeyo Marakwet County, has an estimated cost of Sh38.5 billion. Treasury records show cumulative expenditure of Sh4.978 billion and a reported completion level of 13 per cent, leaving an estimated balance of Sh33.522 billion.
Kimwarer Multipurpose Dam in Keiyo South has an estimated cost of Sh33.5 billion. The project had absorbed Sh3.886 billion and was listed at 12 per cent completion, leaving Sh29.614 billion outstanding. The State Department for Arid and Semi-Arid Lands and Regional Development classified both Arror and Kimwarer as stalled and said negotiations to restart them were continuing.
The two Elgeyo Marakwet projects were launched under former President Uhuru Kenyatta’s administration in 2017 and were initially financed through arrangements involving commercial lenders and Italian export credit support. They later became the subject of procurement disputes, criminal investigations and court proceedings.
In September 2019, a technical committee appointed by President Kenyatta found the proposed Kimwarer project technically and financially unviable and recommended its cancellation. The committee allowed Arror to proceed but proposed a smaller and cheaper design.
Former Treasury Cabinet Secretary Henry Rotich and eight co-accused persons were acquitted on December 14, 2023, in the criminal case connected to the two dams. The anti-corruption court ruled that the prosecution had not produced sufficient evidence to require them to present a defence.
President William Ruto’s administration subsequently reopened discussions on the projects. Kenya and Italy committed in March 2023 to restore cooperation on Arror, Kimwarer and Itare. Cabinet also approved negotiations intended to settle disputes arising from the commercial contracts and financing agreements.
In April 2024, Cabinet approved negotiated settlement terms for Itare and Arror after arbitration proceedings involving Italian contractor CMC di Ravenna were withdrawn. The government said Itare would be completed and construction of Arror would begin. Further discussions were held during President Ruto’s visit to Italy in April 2026, but the latest sector reports still describe Arror and Kimwarer as stalled.
Itare Dam in Kuresoi North, Nakuru County, is estimated to cost Sh35 billion. It had consumed Sh12.066 billion and remained at 27 per cent completion by June 2026, leaving an estimated Sh22.934 billion.
Construction of Itare stopped in September 2018 following contractual and financial difficulties involving CMC di Ravenna. The contract was later terminated, although the government has pursued a negotiated settlement and a new implementation structure to revive the project. Itare was designed to strengthen water supplies for Nakuru and surrounding areas.
The fourth project, Soin-Koru Multipurpose Dam on the border of Kisumu and Kericho counties, requires an estimated Sh23.33 billion to complete. Treasury records put its total cost at Sh25 billion, cumulative expenditure at Sh1.67 billion and completion at eight per cent.
Unlike the three projects linked to Italian-backed financing, Soin-Koru is reported to have stalled mainly because of inadequate government allocations. Its dam works contract was awarded in May 2022 to a joint venture led by China Jiangxi, with construction beginning in August of that year.
Soin-Koru is intended to reduce destructive flooding in the Nyando basin, support irrigation and provide domestic water. The proposed reservoir has a storage capacity of about 93.7 million cubic metres and is designed to supply approximately 72,000 cubic metres of water daily, irrigate about 2,570 hectares and generate 2.5 megawatts of electricity.
The immediate question is how the government will finance the remaining works while meeting debt repayments and other development obligations. Arror and Kimwarer still require completed negotiations and clear implementation terms, while Itare needs the settlement and contractor arrangements translated into work on the ground. Soin-Koru will require fresh budget allocations or an alternative financing structure before meaningful construction can resume.